The method of engineering Installation
•Accessory
Material
1、Line out the horizon baseline
2、Clean up the higher part above baseline,
whiles fill the lower part, so that all the ground are flat to make sure of
installation.
3、Reference to above cement & Sand
matching proportion, and suggest to add some water to make it like flour’s
consistency
4、Put the cement sand evenly to 2
5、After the height adjusted, pick the
quartz tiles out, then put the matched cement sand evenly on the sand, the
humidity of cement sand should be in accordance with stickiness.
6、Put the quartz on cement sand, then
use exclusive rubber drumstick hammer at the surface evenly to make quartz
completely stick to the cement, meanwhile adjust the horizontal quartz tiles’
distance( the gap between tiles should be from 1.5
7.
After installation finished, must wait till 48 hours later to scrap off the
cement sand between the gaps, so as to make sure the bottom cement sand dry
naturally. When scraping off the cement sands, use exclusive stone joint
mixture or white cement adding to pigment (same color as quartz) and some
water, then clean up the overflowed joint mixture with wet textile.( for large
area installation, should make sure the enough gap between tiles, so as to
avoid tiles expanding or turning up.)
8.
If there is heating pipeline when installing, the gap between tiles must be
1、The cement solidification time must
be at least above one month after installation construction finished .
2、No any chemical agent remain are
allowed to leave on the surface. For example, cement drying agent will have bad
influence to the joint of cement and the bottom.
3、The ground must be in flat horizon,
so that to reduce the usage of cement sand at the bottom. Meanwhile, the cement
sand must be churned up averagely.
4、Forbid to use high grade cement and
unverified usable chemical additive and glue.
5、Must use general cement, but don’t
make the ground too wet(namely install drily). If the cement and ground is too
wet, it may cause the joint between cement sand and ground not strong enough,
or even cause delaminating.
•Maintenance
Methods
1、Before normal use, spray stone
exclusive protective agent on the quartz surface(namely stone exclusive
antifouling wax)
2、Then use mop to swab the protective
agent evenly to make it ventilation and drying.
3、Make sure the quartz tiles are clean
and dry before using antifouling wax.
4、For the daily and yearly
maintenance, please reference to marble, but since quartz is hardest and
glossiest among stones, maintenance frequency can be less. Neutral detergent is
suitable for cleaning, but alkaline or acid or other oily chemical cleaning
agents can not be used for cleaning.
•More
Project Cases Illustration
For
mare information about construction methods such as floor & wall
installment, outdoor dry-hang, heterotypic doorpost, pattern/carve, please
reference to the contract or agreement consultation, this part will not do the
detail instructions.